Bradley Road / Barnoldby Road / Waltham Road Roundabout
Bradley Road Roundabout, Waltham
North East Lincolnshire Council are writing to inform you of the junction widening works at the Bradley Road/Barnoldby Road/Waltham Road junction. The works will also include a new footway, new zebra crossing, tactile crossings, traffic signs, carriageway resurfacing and road markings.
These works will begin on Monday 30 March 2026 for 12 weeks and are programmed to be completed on Friday 19 June 2026.
The works will be carried out in 2 phases:
Phase 1 – Civils works (Monday 30 March – Wednesday 10 June)
The removal of the existing traffic islands will be carried out under an overnight road closure at the Bradley Road/Barnoldby Road/Waltham Road Roundabout on Monday 30 March between 7pm and 4am.
Following the removal of existing traffic islands, the main works will begin. From 4am on Tuesday 31 March 2026, 24hr temporary traffic signals will be in place between the Bradley Road/Barnoldby Road/Waltham Road Roundabout and the junction of Barnoldby Road and Sterling Crescent, Waltham.
Please be aware that when the works are within close proximity to Sterling Crescent, access to Barnoldby Road from Sterling Crescent will be closed, however access via Chestnut Road will be maintained.
The phase 1 works are programmed to be completed on Wednesday 10 June 2026.
Phase 2 – Carriageway resurfacing (Wednesday 10 June – Friday 19 June)
The second phase of the works will include carriageway resurfacing and road markings.
These works will be carried out under nighttime road closures between 7pm and 4am, outside of these hours, the road will be fully open.
Please be aware that during the works, on street parking will be temporarily suspended. Please support the contractor by not parking vehicles on the carriageway or footway in the works location to ensure a safe working area can be maintained and to avoid delaying the works programme.
If you have a planned holiday during the construction period (Monday 30 March – Friday 19 June), please ensure your vehicle is parked on your drive or at an appropriate location outside of the closure area. If the works are delayed due to parked vehicles, additional road closures will be required to enable the works to be completed. Footway access will be maintained at all times.
For the duration of the works, the local 9/10 bus services will be affected. These services will terminate at Cheapside and turn around via Kirk Gate. The 11-bus service will continue to operate as normal during the works. Information about the bus diversion routes can be found on Stagecoach’s website:
https://www.stagecoachbus.com/regional-service-updates/east-midlands/grimsby-cleethorpes.
Access for emergency vehicles will be maintained throughout the works. Although every effort will be made to minimise disruption throughout the works, please be aware some elements will be noisy.
Residents with driveways within the works areas will have access maintained at all times.
The council and contractor EC Surfacing Ltd would like to apologise in advance for any inconvenience and assure you that the work will be completed as quickly and safely as possible.
If you have any concerns regarding access, or have questions about the project in general, please use the contact details at the top of this letter or post to us at the address in the footer.
Yours faithfully,
Highways and Transport Team
Municipal Offices, Town Hall Square, Grimsby, North East Lincolnshire, DN31 1HU (01472) 313131, www.nelincs.gov.uk
Find Barnoldby le Beck Parish Council
Barnoldby le Beck Parish Council, Grimsby, Lincolnshire