Purpose Team Status Update

Maintain the VC to ensure Fit for Purpose and to be compliant to legislation and Health and Safety guidelines  

Derek  – Barry, Karen, Lynda, Jackie, Stuart

All interior doors have been changed. Any doors that are fire doors have full FD30 Certification. Non fire doors - toilet doors have been changed to match the fire doors

Clerks office window changed to a FD30 frame and glass

Fire detection upgrade and remote monitoring and call out systems upgrade completed

Electrical compliance works completed

 Replacement of 3 No. windows in attic room with double glazed, acoustic glass and new frames + new frame and double glazing to rear of stage

Major project work on Village Centre roof to include tiling, insulation and new guttering has been agreed by council and has been pre booked to commence w/c 6/5/20