Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

HS2 updates

Notice for temporary overnight closures on B4115 Ashow Road, Stoneleigh

Work item: HS2-BBV-25-1353

Work Item Summary

Project Phase

Phase 1

Region

Warwickshire

Location

Ashow Road

Worksite Name

B4115

Contractor

BBV JV

Type of works

Overnight road closure

Estimated Start Date

11/10/2025

Estimated End Date

13/10/2025

What we are doing

The new realigned B4115 Ashow Road is opening to the public on Sunday 5 October, we have some final minor kerbstone and signage work to complete. In order to complete these works safely we will need to close B4115 Ashow Road overnight.

The B4115 Ashow Road will be closed overnight from Saturday 11 October until Monday 13 October 2025, 8pm – 6am. The road will reopen to the public at 6am on Tuesday 14 October 2025.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

Notice for temporary overnight
closures on B4115 Ashow Road,
Stoneleigh
September 2025| www.hs2.org.uk
High Speed Two (HS2) is the new high-speed railway for Britain. Balfour
Beatty VINCI (BBV) is working in partnership with HS2 Ltd to build the new
high-speed railway in your area.

The work we will be doing
The new realigned B4115 Ashow Road is opening to the public on Sunday
5 October, we have some final minor kerbstone and signage work to
complete. In order to complete these works safely we will need to close
B4115 Ashow Road overnight.
When these works will take place
The B4115 Ashow Road will be closed overnight from Saturday 11
October until Monday 13 October 2025, 8pm – 6am.
The road will reopen to the public at 6am on Tuesday 14 October 2025.

What to expect
You may notice increased levels of construction activity and some travel
disruption. Access for cyclists and pedestrians will be maintained
throughout the works. There will be a fully signed diversion in place to
help drivers navigate their way. Please see the map on page two.

Community drop-in event: Come and talk to us on Monday 17
November 2025 between 2pm and 6pm at the Kenilworth
Centre
This is an opportunity to find out more about upcoming work in the area
and ask our team any questions you may have. Please see further details
on page 3.

If you have a question about HS2 or our works, please contact
our HS2 Helpdesk team on 08081 434 434
or email hs2enquiries@hs2.org.uk

Updated notice of temporary traffic lights and closure of Rugby Road, Cubbington

Work item: HS2-BBV-25-1248

Work Item Summary

Project Phase

Phase 1

Region

Warwickshire

Location

Cubbington

Worksite Name

Rugby Road

Contractor

BBV JV

Type of works

Traffic management

Estimated Start Date

29/09/2025

Estimated End Date

22/11/2025

What we are doing

We recently updated you on works to Rugby Road Overbridge and the permanent road realignment to start on Monday 15 September 2025. These works will now start on Monday 29 September 2025. We require a series of phased traffic management to safely undertake earthworks, utility and highway works.

Phase one: Monday 29 September to Friday 3 October 2025
Two-way temporary traffic lights will be in place 24/7.

Phase two: Monday 6 October to Saturday 1 November 2025. Full road closure will be in place 24/7.

Phase three: Saturday 1 November to Saturday 22 November 2025.
Three-way temporary traffic lights will be in place 24/7.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

Update 10th April 2025

 

Please remember that the A46 will be closed from tomorrow evening at 8pm until 6am on Thursday 1st May:  Notice-of-HS2-works-A46-April-19-day-closure.pdf

 

All the information you need is on the HS2 website:   Notice of A46 closure and lane restrictions, near Kenilworth - HS2 

 

If you have questions, please feel free to come back to me directly, for all public enquiries I’d be grateful if you could direct everyone to the HS2 helpdesk so we have a central record of all enquires.  We will be running a special expediated response service this weekend and over next week to help inform the public and ease any local concerns: Contact us - HS2

 

One final reminder, contrary to some local media reports, there will be two lanes north and two lanes south, open to traffic after the 1st May with a 50mph speed limit in place until we remove the final traffic management on 31st July.   

Notice of full closure on A46 Northbound, near Kenilworth

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-28-08/10/2024

Work Item Summary

Project Phase

Phase 1

Region

Warwickshire

Location

Kenilworth

Worksite Name

A46

Contractor

BBV JV

Type of works

Road closure

Estimated Start Date

25/10/2024

Estimated End Date

26/10/2024

What we are doing

As part of the ongoing works for the construction of the railway we require a full closure of the A46 northbound carriageway. This is to enable the removal and repositioning of the safety barriers back into the verges. Works will take place overnight for one night. The road will be re-opened once the safety barriers are in place and will remain in place until February 2025.

The A46 Northbound will be closed on Friday 25 October, between 8.00pm and 6.00am for one night. Our works will involve a full closure on the northbound carriageway between the Thickthorn Interchange (Leamington) and Stoneleigh Junction.

Please see the notification for diversion routes.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

Last updated:

11th Oct 2024

HS2 Notice of temporary traffic management on B4115 Ashow Road 14th February 2024

HS2 Notice of temporary traffic management on B4115 Ashow Road.pdf File Uploaded: 12 February 2024 186.8 KB