The EGL1 Community Relations Team have been in touch to share information about upcoming vegetation clearance works near Windermere Road bridleway and National Cycle Route 1, which are expected to begin on Monday 23 November.
They need to remove some vegetation, including trees, along sections of both routes. This will make space for them to safely install underground electricity cables next year. The work is espected to take around 2 weeks and they will work between 7.30am - 4.30pm Monday - Friday. These times and dates may be subject to change and they will write to the Parish Council with updates.
Both routes will remain open during this time. They have said that the underground cables in this area will connect the converter station and substation at Hawthorn Pit. Before installation they will need to clear parts of the cable route. They understand that remoing vegetation, particularly trees, may cause concern. They have surveyed the area for widlife and habitats and further checks will take place before works starts. This will hepp identify any measures needed to protect wildlife while the work is carried out.
Replanting will take place after the cables have been installed, during an appopriate planting season. This will give new trees and other vegetation the best chance to establish successfully. Cables are expected to begin being laid in 2027 at which time a temporary diverstion may be needed.
A poster will also be put in place along the route. Please find a copy of this poster and map attached.
Both routes will remain open during the works. At times, users may be asked to wait briefly while we make the area safe for them to pass.
If you have any questions, please do not hesitate to get in touch with them at contact@easterngreenlink1.co.uk or via their website at www.easterngreenlink1.co.uk